Conroe Adopts Data Center Regulations

CONROE – The Conroe City Council has established a new regulatory framework for the growing data center industry, aiming to balance economic development with neighborhood preservation. On August 9, 2023, the council unanimously approved Ordinance No. 2378, which amends Chapter 74 of the city’s code of ordinances to set strict operational and aesthetic standards for future facilities.
The legislation comes as Conroe officials report a surge in interest from developers seeking to capitalize on the region’s proximity to major energy grids and telecommunications infrastructure. According to the Montgomery County Economic Development Council, the broader Houston area has seen a significant uptick in inquiries for industrial space capable of housing server farms, driven by the rapid expansion of cloud computing and artificial intelligence technologies.
Under the new ordinance, prospective data centers are restricted to specific zoning areas: Light Industrial (LI), Heavy Industrial (HI), and the Research and Technology (R&T) overlay district. Beyond zoning, each project must now undergo a rigorous vetting process through a mandatory Specific Use Permit (SUP).
City Administrator Gary Scott stated that the regulations are intended to be proactive rather than reactive. While no official applications have been submitted to the city planning department to date, the council sought to finalize the code to ensure that future facilities meet the long-term expectations of the community.
The new rules place significant emphasis on mitigation of the environmental and aesthetic impact of server facilities. Developers are required to use at least 50 percent masonry on front facades and must maintain a 10-foot landscaping buffer. Building setbacks have been established at 50 feet from residential zones and 25 feet from other zoning districts. To maintain the visual character of the area, all mechanical equipment, including chillers, cooling towers, and backup generators, must be fully screened from public view.
A major point of concern for city officials and local residents remains noise pollution, a common complaint regarding data centers due to the constant operation of industrial-scale cooling fans and power systems. The ordinance mandates that noise levels must not be audible beyond the property line. Applicants are now required to submit an acoustic impact study with their SUP application, detailing plans for sound barriers or low-noise equipment to comply with existing city noise regulations under Chapter 54, Article V.
Utility capacity and backup power protocols are also addressed. Before approval, developers must provide proof of sufficient water, wastewater, and electrical infrastructure. Furthermore, to minimize disturbances to neighboring properties, the ordinance restricts the testing of emergency generators to off-peak hours, specifically between 9 a.m. and 4 p.m., and prohibits the simultaneous testing of more than two generators at any given facility.
The full text of Ordinance No. 2378 can be viewed through the official Conroe City Council agenda portal at cityofconroe.org. As the city continues its rapid growth, these standards signal a shift toward more specialized industrial zoning, ensuring that as Conroe’s skyline evolves, infrastructure projects remain aligned with local residential quality of life.